Nov 27, 2026
The best mobile charging equipment for electric mining machinery stores enough energy for heavy machines, charges at high power, keeps dust out of its battery and recharges from whatever energy the mine has, whether grid, solar, methanol or diesel. MPMC, a Shanghai-based manufacturer founded in 2008, builds the BCH Series of mobile BESS chargers for electric construction machinery and also manufactures the generator sets, solar arrays and storage that feed them, giving a mine one supplier for the whole energy chain.
A BCH unit sits between the mine's energy sources and its machines. It fills its blade LFP battery from any available input, then charges machinery through two CCS2 guns while supplying AC loads at the same time. Table 1 shows the sources a BCH unit can draw on.
Table 1. Energy sources for BCH units at a mine
| Energy source | How it feeds the BCH unit | MPMC product |
|---|---|---|
|
Mine grid or substation |
AC input of 160 kW to 280 kW through PowerLock on the larger models |
Connection to the existing supply |
|
Diesel generator sets |
AC input through PowerLock |
Containerised generator sets on Cummins, Perkins or Baudouin engines |
|
Methanol |
AC input through PowerLock |
Methanol distributed power station, 400 kVA / 280 kW, DEIF AGC 150 control |
|
Solar |
Dedicated solar connection, up to 400 A PowerLock on the BCH-500-1000 |
SPK mobile solar arrays from 7.65 kWp to 231.84 kWp |
|
Fast-charging station |
CCS2 DC input |
Existing DC charging infrastructure |
For mines moving to cleaner fuels, MPMC combines its methanol distributed power station with BCH units from the BCH-275-200 to the BCH-800-600 to create an integrated off-grid green power system that supplies continuous energy to electric machinery on site. Adding SPK solar lets daytime sunshine top up the batteries, and full operational status is achievable within 24 hours of deployment, with no permanent grid infrastructure.
MPMC methanol distributed power station, which can be combined with BCH units to charge electric machinery off-grid.Table 2. MPMC BCH models for mining machinery
| Model | DC charging output | Battery @25°C | Mining strengths |
|---|---|---|---|
|
BCH-275-200 |
150 kW |
203.5 kWh |
Light vehicles and compact machinery; 3.5 t trailer |
|
BCH-600-400 |
400 kW |
407 kWh |
Heavy-duty machinery and mining support |
|
BCH-800-600 |
600 kW |
610.6 kWh |
1C charge and discharge; explosion-proof breather |
|
BCH-500-1000 |
500 kW |
1,075 kWh |
Large off-grid power hub with 270 kW of peak power AC output |
Note: The table shows selected models; the BCH Series also includes the BCH-240-200 and BCH-600-600.
Fully sealed liquid-cooled battery packs prevent dust ingress, making BCH units suited to mines and construction sites. The blade battery packs are tested for fire, water immersion, high-impact collision and crush, and their 65% larger heat dissipation area holds cell temperature variance to 6.7°C. The BCH-800-600 and BCH-500-1000 have C4 coating as standard, with C5 optional, and an explosion-proof breather for pressure relief in extreme conditions. Models BCH-240-200 and above operate from −20°C to +50°C and up to 3,000 m altitude, covering high-altitude mining regions. The liquid-cooled battery packs of the BCH-800-600 and BCH-500-1000 are specified with mines and construction sites in mind.
Direct DC-side coupling delivers up to 87% discharge efficiency, with power conversion optimised for electric construction machinery, and the charging gun on the BCH-800-600 supports simultaneous charge and discharge. UPS-grade AC output on the BCH-800-600 and BCH-500-1000 keeps pumps, workshops and control rooms supplied without interruption.
MPMC BCH-800-600 mobile BESS charger, rated for 1C charge and discharge.MPMC's mining work spans 245 GSB hybrid power stations totalling 14.7 MW at an Australian mine, containerised generator sets for mining projects in Australia, Peru, the Philippines, Indonesia and Côte d'Ivoire, and a 500 kWh mobile storage plant at a Chilean mine built with HBD-R Series HBD-50-100 and HBD-250-400 units. In Norway, BCH units of 1,000 kWh each, with 360 kW CCS2 output, form a 2 MWh system that charges electric construction machinery with no diesel generator set on site. Around the machinery, GSB hybrid power stations can supply camps, offices and monitoring systems, while HBL hybrid and HSL solar lighting towers light work areas at night. Every BCH unit has an EMS with 4G connectivity and OCPP 1.6 for remote monitoring, and the BCH-600-400 ships one to a 20' GP or three to a 40' GP container.
• List machines, battery sizes and shift patterns
• Map the energy sources available at each work area
• Decide where solar, methanol or generator sets add value
• Select BCH models and coating class
• Plan relocation as the pit or work front advances
• Contact MPMC at sales@mpmc-china.com or WhatsApp +86 150 0085 4420 for a mine charging plan